Sizing correction equipment for CKD systems starts with measured load, not motor nameplates alone. Record real power and power factor during normal and low-load periods; pumps and compressors often cycle, changing reactive demand.
Estimate capacitor capacity with: kvar = kW × tan(cos⁻¹ PF₁) − tan(cos⁻¹ PF₂).
For example, correcting a 100 kW load from 0.78 to 0.95 power factor requires about 44 kvar. Treat this as a starting estimate. Verify it against interval measurements and the utility’s billing method.
Check harmonics before selecting capacitors. Variable-speed drives can amplify resonance, so a plain capacitor bank may create problems rather than solve them. IEEE Std 519-2022 sets voltage total harmonic distortion limits at the point of common coupling: 8% for systems up to 1 kV and 5% for systems above 1 kV through 69 kV.
Measure harmonic levels, then consider detuned reactors where needed. Install banks near major loads when practical, with suitable fusing, ventilation, discharge resistors, and clear isolation access. Staged automatic control can follow changing demand.
Commission under real operating conditions and recheck power factor, temperature, and switching behavior. Small details matter. A rushed survey is easy to regret.